Sewerage projects running behind schedule in Jammu, Srinagar
Yash
Khajuria
JAMMU, Nov
08: The
construction work of two major sewerage projects in the state of J&K which
is been awaited completion for many years is likely to delay more, as numerous
problems are being encountered by the agency responsible for carrying out such
works in the Eastern part and this would have adverse impact on the entire
ambitious project.
The
project was started in March 2008 under the Urban Infrastructure and
Development Scheme (UIG) of the Jawaharlal Nehru National Urban Renewal Mission
(JNNURM) is still seems to be inapt to end the multiple problems being faced by
the common masses.
The
State Housing and Urban Development (HoUD) Department is overseeing the
implementation of the projects which is being executed by the National
Buildings Construction Corporations Ltd (NBCC).
In
its official report the HoUD has said that the pace of execution was slow due
to shifting and realigning of BSNL and PHE utilities, site clearance and
extremely narrow and congested areas of the old city. The overall physical
progress achieved with regard to sewerage projects in Jammu and Srinagar stands
at 40 per cent and 45 per cent respectively.
However,
Commissioner JMC K L Khajuria when contacted has said that the project is being
executed by three different agencies that is ERA, NCCC and HoUD, for which they
have been provided the allocation of funds by mean of loan by different
organization besides the funds allocation by the central govt. and they are
working on the said project to finish it off at nearest. Even a sewerage
treatment plant being executed by HoUD, scaling of 27 million litre daily (MLD)
capacity is about to complete in Jammu which is part of the project and it will
complete December 2013.
Pertinently,
the budget allocations by the Central government for the two sewerage systems
are Rs 129.23 crore and Rs 132.92 crore respectively.
Besides
construction of two plants in these cities, sewerage projects also include
laying of trunk, lateral and raider sewer lines across major residential and
commercial areas there and also providing house connections.
The
house connections phase will be taken up only after major sewerage lines are
laid down which is a difficult part because of traffic congestion in commercial
areas and limited space availability in residential areas of the old city, the
official report says.
In
Jammu, sewer lines are being laid in 55.83 kilometers of the city connected to
more than 30,000 homes. In Srinagar, the sewer lines will be connected to
48,000 homes spread across 143.8 kilometer area.
The
HoUD has set 30 September, 2013 and 31 March, 2014 deadline for the sewerage
project completion in Jammu and Srinagar respectively.
Whatsoever
the claims of different authorities over delay in start of work, completion of
already taken up work and digging up of roads in some areas once again, the
fact is that people have been facing numerous difficulties during the past
several years. Each and every agency responsible for the completion of project
and those supervising the execution of the same should ensure that people’s
difficulties are reduced at the earliest.
No comments:
Post a Comment